Disposal & Compliance Logistics

Clean Fill Soil Disposal & Concrete Recycling

Legally compliant, environmentally safe hauling for clean soil, clay, concrete, and asphalt. Fully certified for the new BC Soil Relocation guidelines on Vancouver Island.

What Materials We Hauled & Dumped

We provide full-service dump trucking to certified disposal yards and recycling plants. Different aggregate materials require separate handling to maintain low tipping fees.

Clean Excavation Fill & Clay

Soil, silt, subgrade sands, and clay

Bulk removal of clean soil generated during foundation digging, basement excavation, or trenching.

  • Must be free of wood, roots, metal, and debris.
  • Sod/grass stripped separately to avoid organics fees.

Concrete & Asphalt Recycling

Crushed slabs, driveways, and road rubble

Demolished concrete and asphalt are hauled to processing plants where they are crushed into reusable subbase aggregates.

  • Clean concrete accepted at reduced tipping rates.
  • Reinforced concrete (with rebar) handled separately.

Environmental Compliance (CSR)

BC Contaminated Sites Regulation compliance

Relocating soil under the new March 2023 BC regulations. We work with environmental consultants to haul certified soils safely.

  • Manifest tracking logs provided.
  • Soil Relocation Agreement submissions handled.

BC Soil Relocation Regulation Updates (CSR)

Part 8 of the Contaminated Sites Regulation governs soil leaving Vancouver Island construction sites. If a project moves 30 cubic metres or more of soil off a property with a history of Schedule 2 commercial or industrial use, a Soil Relocation Notification prepared by a qualified professional must reach the Ministry of Environment 7 days before the project starts, and analytical chemical testing may be required. Projects under 30 cubic metres are exempt. We can coordinate with environmental consultants to make this hassle-free.

Our Soil Disposal Workflow

1

Site Assessment & History

We evaluate the excavation location to verify source history (residential vs. commercial/industrial use) and determine if testing is required.

2

Logistics & Load Scheduling

We coordinate the appropriate tandem, tridem, or quad trailer combinations to maximize load capacities and ensure smooth routing to approved yards.

3

Manifest & Relocation Logs

Our drivers collect and maintain dump manifests, weighing receipts, and CSR-compliant relocated volume logs for your project records.

Frequently Asked Questions

Where the fill can actually go

Not one regional-district gate on southern Vancouver Island takes clean soil. These are the private sites that do, with the rate where the operator publishes one and the phone number where it does not.

Need Clean Fill Hauling or Disposal?

We offer efficient tandem and tridem dump truck dispatch for excavations of all sizes. Contact us for a compliant disposal estimate.